DTEK (Elektronaladka LLC), Zelenodolsk

Execution of commissioning works of the automatic control system of the water-chemical mode of the power unit of Art. No. 1 DTEK Kryvorizka TPP:

Unit for preparation of samples, distribution devices (URP);
Switch with electromagnetic/thermal release;
Gas analyzers (Installation work, commissioning work);
Sample preparation block, distribution devices (flow indicator on the hydraulic panel);
Dilution scheme of a three-wire system (cabinet, cells) to 2 (power supply);
Composition measurement system (CMS).

Performance of commissioning work on the field equipment of the ACS TP of power unit No. 1 DTEK Kryvorizka TPP:

Measuring system – pressure sensors;
Measuring system – flow and level sensors;
Temperature measuring systems – temperature sensors;
Equipment state measurement system – discrete sensors;
System for measuring the condition of torch control equipment;
Sample preparation unit, distribution device;
The system for measuring the composition of a substance;
Valve KEG-15/6-0.25;
Elements of signaling, blocking, protection systems;
Measurement of insulation resistance megohmmeter cables, intended for the transmission of electricity to distribution devices;
Measuring the insulation resistance of devices with a megohmmeter;
Elements of automatic control and regulation systems.

Contact us

If you have any questions, we’ll answer them with pleasure

Contact us

If you have any questions, we’ll answer them with pleasure

Request a call

If you have any questions, we’ll answer them with pleasure

Request a call

If you have any questions, we’ll answer them with pleasure

Thanks for your request!
We shell contact you soon!